Opportunities Banner

Kariba Dam - Spillway Refurbishment Phase 2

Launch Date: 
Wednesday, August 30, 2023
Due Date: 
23 November 2023
The Zambezi River Authority, “the Authority”, has received loans and grants from the African Development Bank (AfDB), the Swedish Government and the World Bank’s International Development Association (IDA) toward the cost of the implementation of the Kariba Dam Rehabilitation Project and intends to apply part of the proceeds of these loans and grants to payments under the contract for Spillway Refurbishment Phase 2 which comprise: replacement of the six spillway gate hoists with their associated controls, electrical equipment; to replace the standby diesel generator, completion of the maintenance works on the six (6) spillway gates, repairing concrete and associated miscellaneous civil work. This contract will be jointly financed by the AfDB, Swedish Government and the World Bank.